TABLE OF CONTENTS

Executive Summary   1

1.         INTRODUCTION   2

2.         SUMMARY OF EM&A REQUIREMENTS AND MONITORING RESULTS   4

3.         LANDSCAPE AND VISUAL   7

4.         WASTE MANAGEMENT   8

5.         SITE INSPECTION   9

6.         ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE   11

7.         IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURES   13

8.         Conclusions   14

 

 

FIGURES

 

Figure 1                 Project General Layout

Figure 2                 Air and Noise Monitoring Locations

 

 

LIST OF APPENDICES

 

Appendix A

Construction Programme

Appendix B

Project Organization Chart

Appendix C

Action and Limit Levels for Air Quality and Noise

Appendix D

Graphical Presentation of Monitoring Data

Appendix E

Waste Flow Table

Appendix F

Environmental Mitigation Implementation Schedule (EMIS)

 

 

 

 


Executive Summary

 

   i.   The Civil Engineering and Development Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to undertake the Environmental Team services for the Project and implement the EM&A works.

 

  ii.   This is the nineteenth Quarterly EM&A Report presents the environmental monitoring and audit works for the period between 1 September 2020 and 30 November 2020. As informed by the Contractor, major activities in the reporting period included:

 

September 2020

October 2020

November 2020

·  Utility laying

·  Construction of road base and road pavement

·  Landscape works – irrigation systems, tree and shrub planting

·  Laying Cable and Construction for Road Lighting

 

·  Utility laying

·  Construction of road base and road pavement

·  Landscape works – irrigation systems, tree and shrub planting

·  Laying Cable and Construction for Road Lighting

 

·  Utility laying

·  Construction of road base and road pavement

·  Landscape works – irrigation systems, tree and shrub planting

·  Laying Cable and Construction for Road Lighting

 

 

Breaches of the Action and Limit Levels

 

 iii.   Seven Action Level exceedance for 24-hr TSP were recorded in the reporting period. Five exceedance were recorded at KTD2c on 14, 24 October 2020 and 11, 16, 21 November 2020. Two exceedance were recorded at KER1 on 24 October 2020 and 16 November 2020.

 

iv.   A Limit Level exceedance for 24-hr TSP was recorded in the reporting period. An exceedance was recorded at KTD2c on 5 November 2020.

 

 v.   A Limit Level exceedance for construction noise was recorded. Exceedance was recorded at KTD1 on 21 October 2020. No Action / Limit Level exceedance was recorded for construction noise at KTD2c and KER1 in the reporting month.

 

Complaint, Notification of Summons and Successful Prosecution

 

vi.   No environmental complaint and no notification of summons and successful prosecution were received in the reporting period.

 

Reporting Changes

 

vii.   No reporting changes in the reporting period.